04-07-2004, 12:04 AM
We are in the process of spec-ing a vehicle exhaust removal system in our existing station. Our City's building inspector and engineer say that "sealed" (sealed by a professional engineer or architect) drawings are required for the State mechanical permit. The 2 companys that we are considering (Plymovent & Nederman) both say that sealed drawings are not required and that they have installed hundreds of systems without sealed plans.
Does anyone have any experience on this? I (we) don't want to spend extra thousands of dollars for sealed plans that are not required.
Thanks in advance.
Mark Petersen, Deputy Chief
Menominee Fire Dept.